Sago Landscaping Schedule Announced
Main Entrance to Siena Oaks to Close in June for Bridge Repair
June 12 Update from the city
Allamanda Drive will be closed at the bridge for reconstruction beginning Thursday, June 19, 2014, and will reopen by Friday, August 8, 2014, weather permitting.
The project includes resurfacing of roadways, repairs to pedestrian walkways, spall repairs, crack repairs, repainting of guardrails, and steel sheet piling work. For more information, please contact (561) 804-7034.
May 27 Update
City has advised that repairs to the Allamanda bridge will begin on or about June 9th and continue for 3 to 4 weeks.
Access to Siena Oaks will be from Prosperity Farms on Allamanda past the elementary school. The light at Prosperity is supposed to be adjusted to accommodate increased use by Siena Oaks residents.
Joe Lipofsky – Director SOHA
The City of Palm Beach Gardens is currently engaged in a bridge maintenance program which will include the entrance bridge over the canal at the Siena Oaks entrance from Burns Road. Plans are not set in stone, but the road will likely be closed for three weeks in June.
Jamie Voss, Assistant City Manager and Communications Director, provided the following:
The City is currently updating the plans and will bid the rehabilitation project next month. Staff anticipates construction to start in June and be complete by late July. It will require the shutdown of Allamanda Drive for approximately three (3) weeks.
The contract award will be a council item. The selected contractor will be responsible for the Maintenance of Traffic plan, and the City requires advanced warning signs to go up a minimum of one (1) week before a full road closure occurs